Drawings printed, laminated and ready to go :D
The tower will be 3.5 meters.
The tower will hold four barrels.
Each barrel can contain 5000 liters of water.
See pictures of the tower in Lukunki here and see pictures and info about the project in Lukunki 2012 here.
torsdag den 30. maj 2013
The Danish Team
Anders Flinck - Engineer
The danish head of the project.
Anders lived in Congo from 1989-1990.
He has been the head of many projects in this area.
"Projekt Den Gode Forbindelse" (project the good connection) in 2003 in Mulungwishi, where the electric system was repaired/renewed.
"Projekt Den Gode Forbindelse" (project the good connection) in 2006 in Mulungwishi, where the water system was repaired. Project the Good Connection
"Vand i Mununu" (Water in Mununu) in 2009 in Mununu a village 2 kilometers west of Mulungwishi, where a completely new water system was built. Water in Mununu
"Vand i Lukunki" (Water in Lukunki) in 2012 in Lukunki a village 3 kilometers east of Mulungwishi, where a completely new water system was built. Water in Lukunki
John Holger was in Congo the first time in 2006, he did not see much as he was welding on a hill in Mulungwishi.
John joined the project in 2009 in Mununu, where he again was working all day on a hill.
She has also been part of the four other projects in 2003, 2006, 2009 and 2012.
The danish head of the project.
Anders lived in Congo from 1989-1990.
He has been the head of many projects in this area.
"Projekt Den Gode Forbindelse" (project the good connection) in 2003 in Mulungwishi, where the electric system was repaired/renewed.
"Projekt Den Gode Forbindelse" (project the good connection) in 2006 in Mulungwishi, where the water system was repaired. Project the Good Connection
"Vand i Mununu" (Water in Mununu) in 2009 in Mununu a village 2 kilometers west of Mulungwishi, where a completely new water system was built. Water in Mununu
"Vand i Lukunki" (Water in Lukunki) in 2012 in Lukunki a village 3 kilometers east of Mulungwishi, where a completely new water system was built. Water in Lukunki
John Holger Christensen - Welder
The Welder!John Holger was in Congo the first time in 2006, he did not see much as he was welding on a hill in Mulungwishi.
John joined the project in 2009 in Mununu, where he again was working all day on a hill.
And again in 2012 in Lukunki, a village with no hills, so John played a huge part in building a water tower, a lot similar one that is going to be built in Kyaba.
Jette Flinck - bioanalyst
Jette is married to Anders Flinck, and she also lived in Congo 1989-1990.She has also been part of the four other projects in 2003, 2006, 2009 and 2012.
The Heads of the Project
Anders Flinck has worked together with all five since 2002, and they have all been involved in the prior projects.
Tata Kyoloba Lualaba
Technician
Local Coordinator
Tata Kyoloba Lualaba
Technician
Local Coordinator
Jacques Mulundu
Chauffeur/Mechanic
Plommer on the projects
Chauffeur/Mechanic
Plommer on the projects
Jacques Kyamusa
Farmer
Attendant on the water system in Lukunki
Farmer
Attendant on the water system in Lukunki
Michelle Ngoy
Farmer
All around (hard) worker
Philippe Mwembo
Principal/Chief of primary schools in Mulungwishi district
Admin.
onsdag den 29. maj 2013
Pipes and Fittings from Zambia
Fittings, water pipes, and vessels are bought in Zambia.
It took Phillip, Tata and Jacques 5 days the get the truck across the border.
tirsdag den 28. maj 2013